Advance Notice of Planned Service Interruption: Network Access BJ building Level 2 City East [9:00am - 1:00pm, Saturday 28th October 2023]
Scheduled Maintenance Report for University of South Australia
Completed
The scheduled maintenance has been completed.
Posted Oct 28, 2023 - 13:00 ACDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Oct 28, 2023 - 09:00 ACDT
Scheduled
Advance Notice of Planned Service Interruption
Network Access – BJ Building Level 2 City East

Service(s) Affected: Network Access (wired, wireless, telephony)
Outage Date: Saturday 28th October
Outage Time: BJ Building Level 2 9:00am – 1:00pm
Impact of Interruptions: No network access during the outage window above.
Cause: Network Maintenance
Special Notes: City East Access Layer Refresh Project
Reference#: CHG – 897716
Contact: Josh Petek 0409 697 086
Posted Oct 26, 2023 - 11:46 ACDT